Open the Calculate Plan - Req. Wksh. window.

Calculates a supply plan for items and stockkeeping units that have the Replenishment System field set to Purchase or Transfer.

Note
To calculate supply plans for items that are replenished by production or assembly, you can use the Planning Worksheet window.

The Calculate Plan batch job performs the following steps:

  1. Investigates the demand and supply situation of the item and calculates the projected available balance. The balance is defined as follows:
    Inventory + Scheduled Receipts + Planned Receipts -Gross Requirement
  2. States net requirements for the item.
  3. Creates an item replenishment plan to fulfill net requirements. The plan is presented in the requisition worksheet as detailed order proposal lines that are accompanied by action messages that suggest specific user actions. The action message options are:

Action message Description

New

Creates new supply orders.

Change Qty.

Change quantity on existing supply orders

Reschedule

Reschedules existing supply orders.

Resched. & Chg.

Reschedules existing supply orders and changes the quantity of existing supply orders.

Cancel

Cancels excess supply orders.

You can accept the action message on the requisition line and process it further. If you do not want to accept it, then you can also manually change or delete lines in the requisition worksheet.

When you have approved a requisition line for purchase or transfer, you use the Carry Out Action Msg. - Req. batch job to convert the line to a purchase order or transfer order line.

Options

Starting Date: Specifies the date to use for new orders. This date is used to evaluate the inventory.

Ending Date: Specifies the date where the planning period ends. Demand is not included beyond this date.

Use Forecast: Specifies a forecast that should be included as demand when running the planning batch job.

Respect Planning Parameters Triggered by Safety Stock: By default, this field is not selected.

Supply on planning lines with warnings is normally not modified according to planning parameters. Instead, the planning system only suggests a supply to cover the exact demand quantity. However, you can set the planning run up to respect certain planning parameters for planning lines with certain warnings.

When this field is selected, then planning lines with Exception warnings respect the following planning parameters on the item or SKU card:

Parameter type Reordering policy Parameter

Reorder-Point Parameters

Fixed Reorder Qty.

Reorder Point

Reorder Quantity

Maximum Qty.

Reorder Point

Maximum Inventory

In addition, the following order modifiers are respected:

  • Minimum Order Quantity
  • Maximum Order Quantity
  • Order Multiple

If the field is not selected, then planning lines with Exception warnings are not modified, and only the exact demand quantity is suggested.

Note
In general, exceptional order proposals ensure that the projected available inventory is never lower than the safety stock level. This means that the proposed quantity is just enough to cover the safety stock, without considering planning parameters. However, in some scenarios, order modifiers will be considered.

Tip

See Also