If scrap is produced during processing, it can be entered in the output journal. Note that the scrap quantity does not increase the output quantity.

To post scrap manually

  1. In the Search box, enter Output Journal, and then choose the related link.

  2. In the Posting Date field, enter the posting date.

  3. In the Production Order No., enter the production order number.

  4. In the Item No. field, select the item number.

  5. In the Operation No. field, select the operation that you want to post the scrap to.

  6. In the Run Time field, enter the time that was needed to process the scrap.

  7. In the Scrapped Quantity field, enter the scrap quantity.

  8. In the Scrap Code field, enter the scrap code.

  9. If the warehouse location where the items should be put away uses bins but does not require put-away processing, assign a bin code to the journal line to specify where the items should be placed in the warehouse. For more information, see How to: Assign Bin Codes on Journal Lines.

  10. Click Actions, Posting, Post to post the operations.