When materials have been issued, the actual production operations can start and then be executed in the sequence defined by the production order routing.
An important part of executing production, from a system point of view, is to post production output to the database to report progress and to update inventory with the finished items. Output posting can be done manually, by filling and posting journal lines after production operations. Or, it can be done automatically with the use of backward flushing. In that case material consumption is automatically posted along with output when the production order changes to finished.
As an alternative to the batch journal for output posting for multiple production orders, you can use the Production Journal window to post consumption and/or output for one production order line.
The following table describes a sequence of tasks, with links to the topics that describe them. These tasks are listed in the order in which they are generally performed.
To | See |
---|---|
Print the job cards to be used by machine operators who will read work instructions and enter quantities for output posting. | |
Record and post production output along with material and time consumption, for a single released production order line. | |
Post time spent per operation. | |
Specify the warehouse bin where production output is placed - in warehouses without directed put-away and pick. | |
Batch post produced items and production order value entries for one or more released production orders. | |
Post the number of items produced in each finished operation which do not qualify as finished output, but as scrapped material. | |
Automatically request that warehouse workers put away finished goods by creating the inbound request document when refreshing the inventory or warehouse pick document. | "Create Inbound Request Field" in Refresh Production Order Batch Job |
Put away finished goods according to the warehouse setup. | |
Set a production order to finished, automatically or manually, to indicate that all operations are complete and reported. | |
View information about completed production orders, such as posted entries, comments, and statistics. | |
Calculate and adjust the cost of finished production items and consumed components for financial reconciliation. | |
Use the Capacity Journal window to post consumed capacities that are not assigned to a production order, such as maintenance work. |